Conclusion
No demolition and rebuild is required; the priority is to get three things right — segregation, dedication and traceability.
Key points
- Warehouse zoning: segregate raw material, finished goods and non-conforming goods, with labelling, to prevent mixing.
- Dedicated equipment: Halal lines should be dedicated; shared equipment requires changeover deep-cleaning records and verification of cleaning effectiveness.
- Colour-coded utensils: clean tools, transfer containers and workwear are colour-coded to eliminate cross-use.
- Documents in practice: SOPs, HACCP, the traceability matrix and training attendance must be retrievable on site, not only on paper.
- On-site questioning: auditors often ask line staff at random to confirm the requirements are genuinely applied.
- Biscuits are usually baked, so check whether shortening, emulsifiers and flavourings contain animal-derived components.
Documents to prepare
- Plant layout and production line drawings
- Changeover cleaning work instructions and execution records
- Traceability matrix and batch production records
- Staff Halal awareness training records
- Ingredient declarations for shortening, emulsifiers and flavourings
Scope note
The specific audit checklist and modification requirements are subject to the formal assessment of LHLN and BPJPH.